Green Conveying Chute and Recycling System for Construction Waste: A Case Study

This case examines how a vertical green conveying chute and recycling system for construction waste was deployed across seven towers at the Guangyuan Wanda Plaza project in Sichuan Province. It sets out the project background, the advantages of the system, its working principle, the step-by-step construction method, and the measured recovery and cost-saving results, as a reference for high-rise projects seeking to cut dust, noise and waste-removal costs.

\n1. Project Overview\n

The Guangyuan Wanda Plaza project is located in Wanyuan New District, Guangyuan, Sichuan Province. It is bounded by Binnan Road to the north and by planned roads on the east, south and west sides. With a gross floor area of about 627,000 m2, the development combines residential units, SOHO apartments, office space, a five-star hotel and a pedestrian street, rising to 32 floors above ground with two basement levels. The seven towers already built were each fitted with a green construction-waste conveying chute and recycling system (see Figure 1), enabling resource recovery and a substantial reduction in energy consumption.

\n\"\"\n

Figure 1. Green conveying chute on a floor level

\n2. Advantages of the Waste Conveying Chute and Recycling System\n

Traditional tower waste removal suffers from low efficiency and high labour cost. The green conveying chute and recycling system overcomes these shortcomings and resolves the technical difficulties of clearing waste from high floors. Compared with manual sweeping and carrying, the system offers the following advantages:

\n

1) Through direct comparison, the recycling system raises work efficiency and reduces both labour and material costs.

\n

2) It achieves a higher degree of mechanisation, reduces dust pollution, and is greener and more environmentally friendly.

\n

3) The method makes full use of openings reserved in the floor slabs. Using scrap formwork, fasteners and similar reused materials to form a vertical spoil passage, the installation is reasonable and practical, and integrates waste collection, clearing, transfer, crushing and recovery in one line, while reducing construction-site dust.

\n

4) The chute is quick to assemble and dismantle and can be reused for waste removal across multiple tower buildings.

\n3. Working Principle\n

The green construction-waste conveying chute and recycling system consists of the conveying chute, a crusher connected to the chute through the crusher feed pipe, a storage pit connected to the crusher through the discharge channel, and spray equipment placed on both sides of the crusher. The chute runs vertically along the building. Each floor has a feed inlet; the chute is fixed vertically at the reserved smoke-flue opening and connected to the shear wall around that opening by angle steel, T-section steel and bolts. The chute runs continuously from top to ground level and connects to the crusher feed pipe through a corrugated flexible connector. The crusher feed pipe is curved, and a rubber pad is attached to the curved base corresponding to the chute. The spoil passage and the feed pipe are joined by a soft silicone-cloth connector, which is corrugated in shape. The sections of the crusher feed pipe are connected by flanges and coated with thread adhesive, as shown in Figure 2.

\n\"\"\n

Figure 2. Layout of the crusher and storage pit

\n4. Construction Method\n4.1 Process Flow\n

Selecting the vertical passage → preparation for erection → erecting the conveying chute → crushing and classifying spoil → clearing and unblocking measures → spoil recovery and reuse → dismantling the chute.

\n4.2 Key Operating Points\n4.2.1 Selecting the Vertical Passage\n

Before erecting the green chute, a vertical passage opening must be chosen. The vertical opening must run continuously from the first floor to the top of the building, such as a reserved flue opening or ventilation opening in the tower. The opening size is also critical: an oversize opening creates safety hazards during erection, while an undersize opening produces an unnecessarily narrow chute that is prone to blockage and hurts usability. When selecting the opening, the surrounding conditions should be assessed; an opening with shear walls on both sides is preferred to reduce chute erection cost. To ensure stability, at least one side of the opening must be backed by a wall. The opening should be no smaller than 400 mm × 400 mm and no larger than 800 mm × 800 mm.

\n4.2.2 Erection Preparation\n

1) Technical preparation: before erection, a dedicated construction scheme should be prepared, and the erection crew briefed in writing on the process flow and operating requirements.

\n

2) Material preparation: the formwork, angle steel, T-section steel, expansion bolts, steel plates, vibration-damping pads, compression springs, hinges, rubber pads, flanges and reinforcing steel tubes required for the chute should be ready in advance.

\n

3) Equipment preparation: because scrap formwork is used and is not easy to join, a small cutting saw and a drilling machine should be prepared before erection.

\n4.2.3 Erecting the Conveying Chute\n4.2.3.1 Determining Chute Dimensions\n

According to the size of the reserved opening in the tower, a suitable opening is selected as the chute inlet, with the inlet dimension controlled between 400 mm and 800 mm, as shown in Figure 3.

\n\"\"\n

Figure 3. Plan of the green chute inlet

\n4.2.3.2 Design of Enclosing Formwork\n

Cut the enclosing formwork to the chute dimensions, and number each cut panel to guarantee panel-fit quality and make erection easier for the crew.

\n4.2.3.3 Design of Angle Steel and T-Section Steel\n

Process the angle steel and T-section steel to the chute dimensions. Drill bolt holes along the angle steel at 1,500 mm intervals, with the hole size matched to the bolt diameter.

\n4.2.3.4 Chute Erection Steps\n

Step 1: On the side of the opening backed by a shear wall or brick wall, drill holes in the wall following the holes in the angle steel and T-section steel, one hole every 1,500 mm vertically.

\n

Step 2: Fix the main keel angle steel and T-section steel to the shear wall or brick wall with expansion bolts, and install the enclosing formwork on that side at the same time.

\n

Step 3: Install a 3 mm steel plate over the enclosing formwork already fixed. The plate protects the inner enclosing panel: as waste falls down the chute it can damage the panel, so the plate is mounted on the inner face of the formwork to shield it, as shown in Figure 4.

\n\"\"\n

Figure 4. Steel plates on both sides of the chute inlet

\n

Step 4: Install the vertical formwork and steel plates on the other two sides of the chute, following the same method as the first three steps.

\n

Step 5: Fit compression springs and vibration-damping pads on the inner faces of the left and right chute walls. The compression spring model is 3 × 20D1 × 80, selected in accordance with GB/T 2089—2009, Dimensions and parameters of general cylindrical helical compression springs (coils at both ends closed, ground flat or flattened). The damping pads are made of 4 mm steel plate. The springs and pads cushion the falling spoil; the pads are staggered every 1,500 mm and welded to the inner steel plate with hinges, as shown in Figure 5.

\n\"\"\n

Figure 5. Compression springs and vibration-damping pads

\n

Step 6: Install the formwork on the feed-inlet side. A feed inlet is provided on every floor; its width is at least 300 mm and no more than 600 mm, and its height is controlled between 350 mm and 600 mm. To stop dust escaping through the inlet while waste falls, the inlet is closed with an active hinged panel matching the inlet dimensions. The hinge model is 101.6 mm × 76.2 mm × 2 mm, as shown in Figures 6 and 7.

\n\"\"\n

Figure 6. Vertical schematic of the green waste chute

\n

\"\"

\n

Figure 7. Floor-level feed inlet of the green waste chute

\n

Step 7: Once the vertical chute on the upper floors is complete, build the ground-level storage pit and the crusher mounting platform. A processing shed of the appropriate area is erected on site according to the position of the chute outlet; spray equipment is laid on the ground on both sides of the shed to wet the area and suppress dust. The crusher foundation is prepared in advance, its size depending on the crusher selected, extending about 250 mm beyond the crusher edge on every side, with a downward recess in the middle for discharge. After the crusher arrives, it is placed on the foundation inside the shed; once water and power connections are made, it can be put into use. The crusher is a standard off-the-shelf product, and a suitable model can be chosen to suit site conditions.

\n

Step 8: At the corrugated-connector joint to the spoil passage, reinforcement is provided with a support frame made of Φ48 × 3.5 steel tube. The frame is erected in three horizontal and vertical bays; the bottom tie bar sits 200 mm above the ground, the horizontal bar spacing is 1,500 mm, and the spacing of the third-level horizontal bar follows the height of the corrugated tube but must not exceed 1,500 mm. The corrugated tube is fixed to the support frame, as shown in Figures 8 and 9.

\n\"\"\n

Figure 8. Connection between the green chute and the feed pipe

\n

\"\"

\n

Figure 9. Corrugated tube connected to the spoil passage

\n

Step 9: The whole system, from erection preparation to a working installation, takes about one week. During use the following points must be observed: Ø after the chute is formed, waste must be sorted before it is discharged down the passage; Ø rebar, formwork, timber, and plastic must not be thrown into the green passage; Ø once erected, the top inlet must be sealed to prevent rainwater entering through the top and dust escaping through it and causing air pollution; Ø if a blockage is found during use, stop tipping spoil into the chute and resume only after it has been cleared; Ø above every floor inlet, affix a notice stating that only spoil-clearing personnel may open the inlet.

\n4.2.4 Crushing and Classification of Spoil\n

Once the chute is erected, spoil cleared from the floors is stacked as recyclable and non-recyclable waste. Recyclable spoil travels down the chute to the ground floor, where it is crushed and stored by class in the storage pit; non-recyclable waste passes down the chute to ground level and is then transferred to the waste pool.

\n4.2.5 Spoil Clearing and Unblocking\n

1) Spoil clearing: concrete blocks, discarded bricks, floor-dropped mortar and other spoil left over from the primary and secondary structural works are cleared from the floors. After classification, larger pieces are crushed to under 30 cm in diameter before passing through the chute inlet to the ground-floor bunker for crushing. Unauthorised personnel must keep clear of the spoil passage during clearing; a designated person is responsible for the chute, and floors must be cleared one at a time rather than several floors together.

\n

2) Unblocking measures: if falling spoil blocks the chute, the crew should stop feeding spoil into the inlet and check floor by floor to locate the blockage. Once located, a clearing rod is used from the inlet on the floor above the blockage; the clearing personnel must never put a hand or head into the inlet passage. If the rod cannot clear it, the enclosing formwork at the blocked section is removed, and the panel is reinstated promptly after the spoil is cleared.

\n4.2.6 Recovery and Reuse of Spoil\n

Spoil crushed by the crusher—such as floor-dropped mortar, concrete blocks and bricks—can be reused for backfilling basement slabs that require fill and rooms with dropped floor levels, or reprocessed into lightweight partition blocks and similar products.

\n4.2.7 Erection and Dismantling Time\n

1) Erection time: the chute is installed after the primary structure is complete and the secondary-structure brickwork and plastering are finished; erection takes one week.

\n

2) Dismantling time: after all spoil in the building has been cleared, the green chute is dismantled promptly from top to bottom; the whole removal takes two days.

\n5. Conclusion\n

Across the entire construction period, the seven high-rise towers of the Guangyuan Wanda Plaza project used the green conveying chute and recycling system for construction waste. The construction-waste recovery rate reached 50%, and total cost savings amounted to RMB 212,300. The system meets the requirements of green construction, energy saving and emission reduction; it avoids the heavy dust and noise associated with clearing construction waste, keeps the interior of the floors tidy, and satisfies green construction standards. Most importantly, it achieves resource recycling, raises equipment utilisation, saves the large measure costs spent on conventional waste removal, creates secondary value, and significantly lowers energy consumption.