The construction waste chute is installed on the exterior wall or structure of a building; hoisting and fixing are key steps. Longkang offers various hoisting and fixing methods to suit different engineering conditions. This article explains in detail.
- Hoisting Methods
- Manual Hoisting (Low-rise)
- Applicable: height ≤10 m
- Method: manually lift with ropes
- Personnel: 2–3 people
- Tools: ropes, hook
- Advantage: no tower crane required
- Disadvantage: working-at-heights risk
- Tower Crane-Assisted Hoisting (High-rise)
- Applicable: height >10 m
- Method: tower crane lifts one section into position
- Personnel: 2 ground crew + 2 floor crew
- Advantage: safe and efficient
- Note: must not affect normal tower crane operations
- Electric Hoist Hoisting
- Applicable: inside elevator shaft or dedicated track
- Method: electric hoist lifts along the track
- Advantage: continuous operation
- Suitable for: super high-rise buildings and long-term use
- Classification of Fixing Methods
- External Scaffold Fixing (Most Common)
- Utilize scaffolding or external scaffold
- Connect clamps to external scaffold uprights
- Applicable: main structure construction phase
- Advantage: no need to anchor into the structure
- Disadvantage: needs re-fixing as the external scaffold is dismantled
- Structural Anchor Fixing
- Anchor into structural beams or walls with chemical anchors
- Applicable: after external scaffold removal or for permanent fixing
- Advantage: firm and reliable
- Disadvantage: requires a structural surface
- Anchor specification: M12 chemical anchor
- Triangular Bracket Fixing
- Weld triangular brackets onto the structure
- Fix clamps onto the brackets
- Applicable: chute is far from the structure
- Advantage: highly adaptable
- In-Elevator-Shaft Fixing
- Utilize the elevator shaft
- Fix brackets to the shaft wall
- Applicable: indoor chute
- Advantage: does not affect the facade
III. Fixing Point Layout
- Fixing Point Spacing
| Building height |
Fixing point spacing |
| ≤30 m |
4–5 m |
| 30–60 m |
4 m |
| 60–100 m |
3–4 m |
| >100 m |
3 m |
- Fixing Point Positions
- At the clamp seat in the middle of each section
- Fixing points must be provided at buffer sections
- Fixing points must be provided at elbow sections
- Reinforced fixing at the bottom
- Fixing Point Load
- Each fixing point bears: chute self-weight + waste weight + wind load
- Safety factor ≥3
- Anchor tensile resistance ≥10 kN
- Clamp Installation
- Clamp the clamp seat onto the middle of the chute
- Wrap the clamp steel band around
- Connect to the fixed bracket
- Tighten the bolts
- Insert rubber pads between clamp and chute (anti-slip, anti-wear)
- Wind Load Reinforcement
- Guy Ropes
- Provide guy ropes every 20 m on super high-rise chutes
- Diagonally tie to the structure
- Reduce chute sway
- Lateral Braces
- Provide lateral braces every 15 m
- Connect to adjacent structures
- Restrict chute displacement
- Fixing Quality Inspection
- All fixing points firm
- Chute does not wobble
- Anchor pull-out test (sampling inspection)
- Chute stable under wind load
- Check for looseness daily
VII. Longkang Fixing Solutions
- Recommend fixing methods based on building conditions
- Provide fixing point layout drawings
- Supply matching clamps, anchors, and brackets
- On-site installation guidance
- Acceptance inspection of fixing firmness