After the construction waste chute installation is complete, acceptance must be carried out; it may be put into use only after confirming safety and reliability. This article explains the acceptance standards in detail.
Construction drawings
Product technical requirements
Safety operation procedures
Relevant safety specifications
Product certificate of conformity
Material test report
Installation records
Fixing point load calculation (high-rise)
Safety briefing records
III. Appearance Acceptance
Chute appearance intact, no damage
Uniform color
Signs complete
No deformation
Buffer sections in correct position
| Item | Permissible deviation |
| Chute verticality | ≤1°/3m |
| Fixing point spacing | ±0.5 m |
| Feed inlet height | ±50mm |
| Discharge outlet height | ±50mm |
| Total chute length | ±100mm |
Sealing rings in place at all joints
Buckles tightened
No gaps at joints
Sealing check (no leakage under water spray)
Joints remain tight after 3 repeated loadings
All fixing points firm
Anchor bolts not loose
Clamps tightened
Chute does not wobble (hand-push test)
Stable under wind load
VII. Functional Acceptance
Load light objects (wood blocks, plastic)
Observe smooth falling
Check for blockage
Check smooth discharge at the bottom
Load standard blocks
Check bottom speed (listen to sound)
Check if buffer sections work normally
Opens and closes smoothly
Closes tightly
Does not open automatically
Waste discharges smoothly
Dust controlled
Collection hopper receives normally
VIII. Safety Acceptance
Warning signs complete
Protective canopy intact
Warning zone set up
Reliable grounding (high-rise)
Safety pins installed
Qualification criteria:
Documentation complete
Appearance intact
Dimension deviations within tolerance
Joints sealed
Fixing firm
Functions normal
Safety protection in place
Non-conformance handling:
Re-accept after rectification
Do not use if non-conforming
Record problems and rectification
Constructor sign-off
Supervisor sign-off
Safety department sign-off
Hand over to user
Provide acceptance form
On-site acceptance guidance
Assist with rectification
Deliver for use after passing acceptance
Usage training