This utility model is an environmental-protection waste conveyance duct for high-rise building construction. It consists of a number of large-head-shaped short pipe sections connected end to end, together with mutually fixed hangers and connectors. The duct is fixed to the support frame on the high-rise building body, with a buffer pipe inside the duct. The buffer pipe is arranged in an L-shape, connected to the duct by threads, and placed within a buffer layer. When construction waste must be conveyed, it can be guided to the ground through the duct. As waste descends to the ground inside the duct, it is buffered internally by the L-shaped buffer pipe; the L-shaped structure supports the vertically falling waste, reduces the effect of gravitational acceleration, and the buffer layer releases the impact force to provide good cushioning and damping.

Technical background: In high-rise construction, solid waste such as concrete fragments, brick rubble, mortar residue and decoration debris must be conveyed from each floor to the ground. Manual carrying floor by floor or elevator transfer is inefficient and occupies vertical transport resources; direct overhead throwing risks falling-object injury and equipment damage, and produces dust and scattered debris. A relatively enclosed, continuous vertical duct that lets waste slide down by gravity to a ground collection point is a common approach balancing safety, efficiency and environmental protection.
Structure: The system mainly comprises pipe sections, hangers, connectors, body support, buffer pipe and buffer layer. The sections are large-head short pipes connected end to end to form the vertical duct; hangers and connectors fix adjacent sections to each other and suspend or support the whole duct on the building body frame. Supports are arranged according to site structure and openings and can attach to the window side, floor slab, wall or scaffold. The buffer pipe is placed at a suitable position inside the duct in an L-shaped deflection arrangement, threaded to the duct for easy removal and replacement; a buffer layer outside and around the buffer pipe absorbs and releases impact energy. A bottom outlet and collection container gather the waste for truck removal.
Buffering principle: Waste enters from the floor inlet and slides along the wall; when it passes the L-shaped buffer pipe, the deflection supports and slows the vertically falling waste, changing its direction and cushioning the impact of gravitational acceleration. The buffer layer further absorbs impact energy on the sections, reducing noise and vibration and preventing the waste from striking the bottom outlet and collection container at high speed. After multi-stage buffering, waste reaches ground more gently, lowering wear on the duct, supports and collection facilities.
Benefits: Enclosed transport keeps dust and scattering inside the duct; the buffer structure reduces descent impact and noise, protecting the duct and bottom facilities; modular sections and standardized connectors are easy to assemble, dismantle and reuse; the flexible support attachment suits different structures and construction phases; and replacing overhead throwing removes falling-object hazards, meeting civilized and green construction requirements.
Applications: Main works and decoration phases of high-rise residential, office, commercial and public buildings such as hotels and hospitals, old-building demolition, and other projects requiring centralized enclosed conveyance of solid waste from height to ground. Matching supports, chain ears, dust-suppression spray, bottom outlet and collection bin can be selected by site conditions; connectors, buffer pipe and support wear should be inspected regularly and damaged parts replaced promptly.
Comparison with a plain straight chute: A plain straight chute lets waste slide down the straight wall by gravity; fragments strike the wall and bottom at high speed, causing noise, rapid wear and heavy bottom impact in high-rise or heavy-duty conditions. The buffered environmental duct places an L-shaped buffer pipe and buffer layer inside; deflection and energy absorption reduce the speed and impact at the bottom, extending the life of the duct and collection facilities and lowering drop noise on floors and surroundings. The threaded buffer pipe can be removed and replaced alone when worn, without dismantling a whole duct section.
Project coordination and reuse: Sections nest for transport and are erected in series by floor height; support attachment is chosen from the window side, slab, wall or scaffold. At project end, sections are dismantled and recovered for reuse on the next project. The supplier can provide chute configuration, support scheme and matching buffer and dust accessories according to site structure and waste type, plus installation and maintenance guidance, so the duct keeps delivering safe, enclosed, dust-controlled conveyance in high-rise works, renovation and demolition removal.
Installation and acceptance points: Before installation, check that all sections, hangers, connectors, buffer pipes and buffer layers are complete and sound. Erect the duct vertical and coaxial, fasten connections properly, and place supports and anchors on structural load-bearing parts; the buffer pipe direction and deflection angle should follow the design. Acceptance focuses on duct enclosure, connection tightness, support anchoring reliability and the fit between the bottom outlet and collection container. In use, inlet openings need retaining edges and warnings, and the bottom outlet is fenced and managed; clean attached debris from the duct regularly and inspect the buffer pipe for wear or deformation, repairing or replacing loosened, cracked or failed parts promptly for long-term safe and stable operation.